Example Asbestos Removal Projects in Westminster, California

The seven example jobs below cover manufactured homes and tract houses, from a bathroom floor to a house demolition. Each one lists what was sampled, what came out, the work days and an estimated cost.

Bathroom floor removed from a single-wide before a walk-in shower goes in

Example project

Home
1970s single-wide manufactured home in Westminster with one bathroom and a tub
Original request
Replace the tub with a walk-in shower and lay a new floor
Testing
A Cal/OSHA-certified asbestos consultant samples the sheet vinyl, the glue and the wall panel seams in the bathroom
Found
Asbestos in the sheet vinyl and its glue
Clear
The wall panel seams
Area
About 40 sq ft of bathroom floor
Timeline
Less than 100 square feet in a renovation, so no district notice, then one working day
Cost
$2,000

Scope of work

The bathroom and the entry door sealed with plastic and a filter running, the vinyl lifted and the glue removed wet, bagged disposal and a cleanup. The survey, the tub removal, the shower and the new floor are separate.

Project overview

In this example, the owner of a 1970s single-wide in Westminster wants a walk-in shower where the tub sits. The rule has no carve-out for manufactured homes, so the survey comes first, as in any other house.

The floor vinyl and its glue test positive. The job removes less than 100 square feet, so no district notice is needed, and the abatement crew finishes in one day before the plumber starts.

The goal

The goal is a bare bathroom floor, so the shower pan is set over a surface with nothing positive on it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the vinyl, the glue and the wall seams.
  2. Results The lab marks the vinyl and the glue positive and the wall seams clear.
  3. Work day The bathroom is sealed and the floor layers are removed wet.
  4. Then The plumber removes the tub and sets the shower pan.

Planning right

  • Plan a place to wash up on the work day.
  • Take towels and cabinet contents out of the bathroom.
  • Tell the plumber which layers tested positive.
  • Ask the park office about work hours.

Get a free quoteMore about mobile and manufactured home asbestos removal

Textured ceiling panels cleared from a double-wide before a remodel

Example project

Home
1970s double-wide manufactured home in Westminster with textured ceiling panels in the living room, kitchen and hall
Original request
Repaint the ceilings and swap the light fixtures as part of a remodel
Testing
A Cal/OSHA-certified asbestos consultant samples the panel coating and the seams in the living room, the kitchen and the hall
Found
Asbestos in the panel coating in the living room and the hall
Clear
The kitchen coating
Area
About 700 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$6,200

Scope of work

The home sealed room by room with air filters running, the positive coating wetted and scraped into bags, a HEPA clean and the haul. The survey, the district notification fee, the clearance air test, the repairs and the paint are separate.

Project overview

In this example, a couple is remodeling their 1970s double-wide and wants new lights and clean ceilings. Manufactured homes follow the same survey and notice rules as any dwelling, so a consultant samples first.

The coating in the living room and the hall tests positive and the kitchen coating is clear. The ceilings add up to more than 100 square feet, so the abatement contractor files the district notice online.

The goal

The goal is bare ceiling panels in the affected rooms, so the new paint and lights go on a clean surface.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the coating in three rooms.
  2. Before work The abatement contractor files the district notice online.
  3. Days one to three Each affected ceiling is sealed and scraped in turn.
  4. Last An independent consultant tests the air, then the painter starts.

Planning right

  • Ask the consultant to sketch which panels were sampled.
  • Move furniture to one end of the home.
  • Order the light fixtures after the air results.
  • Do not cut into the panels before the visit.

Get a free quoteMore about popcorn ceiling removal

Wall and floor material removed before an old house is demolished

Example project

Home
1960s one-story house in Midway City, an unincorporated community, with textured ceilings, wall compound and kitchen vinyl
Original request
Demolish the house and clear the lot for a new home
Testing
A Cal/OSHA-certified asbestos consultant surveys the house and the detached shed, sampling every layer
Found
Asbestos in the wall compound, the ceiling texture and the kitchen vinyl
Clear
The roof layers and the shed
Area
About 1,700 sq ft of wall, ceiling and floor material
Timeline
Notice no later than 10 working days ahead, then four working days before the wrecking crew
Cost
$21,000

Scope of work

Rooms sealed in turn with air filters running, the three positive materials removed wet, labeled bags, air monitoring and the haul with its paperwork. The survey, the district notification fee, the clearance air test and the demolition are separate.

Project overview

In this example, the owner of a 1960s house in Midway City is clearing the lot. OC Public Works takes an asbestos disclosure for demolition projects, where the contractor attaches each notice sent to the district or states that none is involved.

The wall compound, the ceiling texture and the kitchen vinyl test positive, so a notice goes in and is attached to the disclosure. The abatement crew removes the three materials, and the wrecking crew follows.

The goal

The goal is a house stripped of its positive materials, so the lot is cleared with the paperwork in order.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant surveys the house and the shed.
  2. Before work The abatement contractor files the district notice online, and a copy goes with the county disclosure.
  3. Days one to four The rooms are sealed one at a time and the three materials come out wet.
  4. Last An independent consultant tests the air, then the wrecking crew starts.

Planning right

  • Keep the district notice with the permit papers.
  • Ask the abatement contractor for the haul paperwork.
  • Give the wrecking crew a copy of the survey.
  • Mark the shed on the site plan.

Get a free quoteMore about renovation and demolition abatement

Two layers of kitchen vinyl removed from a manufactured home

Example project

Home
1970s manufactured home in Stanton with a small kitchen and two layers of sheet vinyl
Original request
Strip the old vinyl and lay a new kitchen floor
Testing
A Cal/OSHA-certified asbestos consultant samples the top vinyl, the lower vinyl and the glue under each
Found
Asbestos in the lower vinyl and its glue
Clear
The top vinyl and its glue
Area
About 90 sq ft of kitchen floor
Timeline
Less than 100 square feet in a renovation, so no district notice, then one working day
Cost
$1,900

Scope of work

The kitchen sealed from the rest of the home with a filter running, both layers lifted and the lower glue removed wet, bagged disposal and a cleanup. The survey and the new floor are separate.

Project overview

In this example, the owner of a 1970s manufactured home in Stanton is replacing the kitchen floor. The top vinyl covers an older layer, and a consultant samples both layers before either comes up.

Only the lower vinyl and its glue test positive. The job removes less than 100 square feet, so no district notice is needed, and the abatement crew takes both layers up in one day.

The goal

The goal is a bare kitchen floor, so the new covering is laid over a surface with nothing positive on it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples each vinyl layer and its glue.
  2. Results The report marks the lower vinyl and its glue positive and the top layer clear.
  3. Work day The kitchen is sealed and both layers are lifted, the lower glue removed wet.
  4. Then The new floor goes in.

Planning right

  • Empty the lower cabinets the evening before.
  • Plan meals away from the kitchen on the work day.
  • Choose the new floor while the crew works.
  • Keep the report with the home papers.

Get a free quoteMore about floor tile and mastic removal

Wall compound removed before a partition comes out of a tract house

Example project

Home
1960s tract house in Westminster with a partition wall between the kitchen and the den
Original request
Take out the partition and open the kitchen to the den
Testing
A Cal/OSHA-certified asbestos consultant samples the joint compound and texture on both faces of the wall
Found
Asbestos in the joint compound on both faces
Clear
The wall texture
Area
About 160 sq ft, both faces of the partition
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$3,700

Scope of work

The kitchen and den sealed with air filters running, the positive compound removed wet from both faces, bagged disposal and a cleanup. The survey, the district notification fee, the clearance air test, the wall demolition and the finish work are separate.

Project overview

In this example, a family is opening the kitchen of their 1960s tract house to the den. The plans show the wall as a partition, so the work counts as renovation, and the survey comes first.

The joint compound tests positive on both faces. The two faces add up to more than 100 square feet, so the abatement contractor files the district notice online before the crew starts.

The goal

The goal is a wall with the positive compound gone, so the remodel crew takes it out without disturbing it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples both faces of the wall.
  2. Before work The abatement contractor files the district notice online.
  3. Days one and two The rooms are sealed and the compound is removed wet from both faces.
  4. Last An independent consultant tests the air, then the remodel crew takes the wall out.

Planning right

  • Clear the counters on the wall side.
  • Ask the remodel crew to confirm the wall is a partition.
  • Keep the report with the plans.
  • Hold the cabinet order until the air results.

Get a free quoteMore about drywall, joint compound and plaster removal

Wrapped attic ducts removed before new return-air ducts are run

Example project

Home
1970s two-story house in Westminster with a furnace in the garage and ducts through the attic
Original request
Add return-air ducts upstairs and replace the old supply runs
Testing
A Cal/OSHA-certified asbestos consultant samples the wrap on the trunk, a branch and the seam tape
Found
Asbestos in the wrap on the trunk and branches
Clear
The seam tape
Area
About 220 ft of attic duct
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$4,700

Scope of work

The attic hatch sealed and the ceiling below covered, the wrapped ducts removed wet into labeled bags, bagged disposal and a cleanup. The survey, the district notification fee, the clearance air test and the new ducts are separate.

Project overview

In this example, the owners of a 1970s two-story house want better airflow upstairs. Taking out or putting in HVAC ducts counts as renovation under the district rule, so the old wrap is sampled first.

The wrap on the trunk and the branches tests positive. The abatement crew removes every run, and the HVAC crew hangs the new returns in a clean attic.

The goal

The goal is an attic with the old wrapped ducts gone, so the new returns go in on a cleaned job site.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap and tape at three spots.
  2. Before work The abatement contractor files the district notice online.
  3. Days one and two The hatch is sealed and the ducts are wetted, cut apart and bagged.
  4. Last An independent consultant tests the air, then the HVAC crew starts.

Planning right

  • Clear the garage near the furnace.
  • Send the report to the HVAC contractor.
  • Plan for the system to be off on the work days.
  • Ask about the new duct layout before the work starts.

Get a free quoteMore about HVAC duct and pipe insulation removal

Whole-house survey of a rental house between tenants

Example project

Home
1960s rental house in Westminster, vacant for the week between two tenants
Original request
Find out what the ceilings and floors hold before any refresh
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture in each bedroom, the floor tile and mastic and the wall compound, 17 samples in all
Found
Asbestos in the ceiling texture in two bedrooms and in the mastic under the kitchen tile
Clear
The other ceilings, the hall floor and the wall compound
Timeline
Lab results first, then the removal is booked before the next tenant
Estimated testing cost
$1,100

Scope of work

A visit by the consultant, 17 samples across the house, a lab result for each and a written report with the spots marked. Removing the materials is priced on its own.

Project overview

In this example, a landlord has a rental house empty between tenants and wants to know what is in the ceilings and floors. The survey covers the whole house, so any later refresh starts from known facts.

The texture in two bedrooms and the mastic under the kitchen tile test positive. The landlord books the abatement crew for those three spots and leaves the rest of the house as it is.

The goal

The goal is a written record of the whole house, so every later job starts from known facts.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceilings, the floors and the walls.
  2. Results The report marks three materials positive and lists each clear spot.
  3. Next The landlord books the abatement crew for the three positive spots.
  4. Then The refresh goes ahead after the work and the air results.

Planning right

  • Give the consultant a key for the day.
  • Ask for the report with a floor plan of the sample spots.
  • Keep the report for the next turnover.
  • Hold the refresh schedule until the lab results are in.

Get a free quoteMore about asbestos testing and surveys

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (657) 227-1485

Call (657) 227-1485